Cost Formula Decomposition
How to Calculate High-Low Method Cost Calculator (Formula & Method)
Fixed Cost (a) = Total Cost – (b x Activity)
Cost Formula: Y = a + bX
The High-Low Method separates mixed expenses (such as factory utilities, machine maintenance, or delivery fleets) into their fixed and variable elements using only the highest and lowest historical activity periods.
Worked Example with Numbers
Peak month: 8,000 machine hours, $34,000 cost. Lowest month: 3,000 machine hours, $19,000 cost. Change in cost = $15,000. Change in hours = 5,000. Variable rate = $15,000 / 5,000 = $3.00/hour. Fixed base = $34,000 – ($3.00 x 8,000) = $10,000. At 6,000 hours, total cost is $10,000 + ($3 x 6,000) = $28,000.
Common Student & Practitioner Mistakes
- Selecting high and low based on dollars instead of activity: You must always pick periods based on highest and lowest operational activity (hours or units), not cost.
- Distortion from outlier months: A month with an abnormal breakdown or storm will distort the entire equation.
Frequently Asked Questions
How does High-Low compare to Least-Squares Regression?
Regression uses all historical data points and is more statistically reliable; high-low is faster and requires no statistical tools.
What is the relevant range?
The activity range between low and high volume within which fixed costs remain fixed and variable unit costs remain constant.