What Is Job Costing (Job-Order Costing)? Definition & Workflow

The gold standard cost tracking system for unique, made-to-order products and services.

Home › Accounting Glossary › Job Costing

Quick answerJob costing (or job-order costing) is a cost accounting system that tracks, records, and accumulates manufacturing costs (direct materials, direct labour, and allocated overhead) separately for each individual custom order, contract, batch, or unique project.
Also calledJob-order costing, contract costing, project costing
Compare withProcess Costing (for mass continuous identical products)
IndustriesCustom construction, aerospace, printing, consulting, bespoke software

Job costing in plain English

If a shipyard builds three luxury yachts, each yacht will have distinct blueprints, luxury finishes, engine specifications, and construction times. You cannot divide total shipyard costs by three.

Instead, the accounting team creates a dedicated Job Cost Sheet for Yacht #1, Yacht #2, and Yacht #3. Every purchase order of teak wood, every welder’s timesheet, and a share of shipyard overhead are recorded on that specific yacht’s ledger.

The three pillars of a job cost sheet

Total Job Cost = Direct Materials Traced + Direct Labour Traced + Applied Overhead

Where Applied Overhead = Predetermined Overhead Rate × Actual Cost Driver Consumed.

Worked example

Apex Architectural signs Contract #404 to design and fabricate a custom steel staircase:

Cost CategoryDocumentation SourceCalculation DetailsAccumulated Cost
Direct MaterialsMaterial Requisitions #12-15Steel beams, glass panels, bolts$18,500
Direct LabourEmployee Time Tickets #88-92140 welder/fitter hours @ $32/hr$4,480
Manufacturing OverheadApplied at $25/direct labour hr140 direct labour hrs × $25/hr$3,500
Total Manufacturing Cost (Job #404)Job Cost Sheet Summary$18,500 + $4,480 + $3,500$26,480
Contract Billed PriceCustomer InvoiceAgreed client contract price$38,000
Gross Profit on Job #404Profit Margin = 30.3%$38,000 – $26,480$11,520

Common mistakes

Common mistakes
  • Using actual overhead instead of applied overhead: Companies cannot wait until the end of the year to know utility bills before pricing a job; they must use a predetermined applied overhead rate.
  • Failing to track scrap to specific jobs: If a custom job requires specialized exotic wood that breaks, that scrap should be charged to that job unless it is a general factory defect.

Frequently asked questions

What is a Job Cost Sheet?

A Job Cost Sheet is the primary accounting document that records all direct materials, direct labour, and manufacturing overhead charged to a specific job.

Can service firms use job costing?

Yes. Law firms, accounting practices, advertising agencies, and consulting firms use job costing to track billable partner hours and expenses to specific client matters.